Mozambique

CLIENT ~ Aggreko
PROJECT ~ Ressano Garcia, Mozambique
DESCRIPTION ~ 275 kV Substation and 1.5 km of 275 kV overhead lines
NIC was the EPCM Contractor on this project and was responsible for the following:

Approved engineering
Appointed subcontractors for Civils and Engineering
Carried out the electrical installation
  • Stringing of HV lines
  • Control and Signal Cabling
  • MV Installation
  • Panel fitment and protection
Carried out the mechanical including
  • Installation of Gantry Structures
  • All HV Equipment Structures

Maintained overall responsibility for the completion and success of the Project

What makes this project truly groundbreaking is the length of time it took to complete. A "normal" project of this nature takes anywhere from 6 to 12 Months to complete. NIC achieved this in 2 months; something we think has never been achieved before!!
DURATION ~ 10 May 2012 on site work began to 15 July 2012
REFERENCE ~ Roy Cursley